Jobsite Photos:
I-40 Mississippi River Bridge Offramp
Memphis, TN
¾ x 4 3/16 Headed Shear Connectors shot to expansion joints/bridge transitions. This was a retrofit to the I-40 Mississippi River Bridge, East bound off ramp. Studs were damaged when the concrete was removed and they hired Elrod Stud Welding to install the replacements.
Equipment used: Tru-Weld Equipment 205 KW Generator and TWE SC-3402 Dual Gun Stud Welder with TWE17000 HD Stud Guns and Thru-Deck accessories.
Please see our Arc Stud Welding Equipment Page for detailed specs and information on the equipment used.